Underground and Aboveground Storage Tanks

  • Release investigations
  • Spill prevention, control and countermeasures (SPCC) plans
  • Oil discharge contingency (ODC) plans
  • Secondary containment integrity evaluations
  • AST systems and fuel dispensing design

Example Projects:

Virginia Department of Corrections, Term Contract for Environmental Engineering Services, Statewide. Prepared a UST/AST management plan for regulatory compliance of over 250 tanks (AST, UST and propane) at 35 facilities. Implemented first and second phase of compliance including UST and AST registration, bid packages/specifications for UST closure and AST installation, soil and groundwater sampling and analysis, multiple Site Characterization Reports and Corrective Action Plans for leaking underground storage tanks, UST closure documentation, and negotiation of a Compliance Agreement with the DEQ. Also provided training on UST/AST compliance and monitoring requirements. Prepared Spill Control and Countermeasure Plans (SPCC) and Oil Discharge Contingency plans (ODC) for multiple facilities. Other tasks included preparation of a NEPA document for a proposed 1500-bed medium security prison, asbestos and lead paint surveys of two prisons, and wetland/water quality permitting and Environmental Impact Report for a new dam on Kimberling Creek in Bland County.
Client: Virginia Department of Corrections
Fees: $500,000
Completion Date: 2/2002

Oil Spill Prevention, Control, and Countermeasures Plan (SPCC), Virginia Department of Corrections Sussex 1 and 2 Facilities. Prepared a SPCC Plan and an Oil Discharge Contingency Plan (ODC) for the Sussex 1 and 2 Correctional Facilities. The project included evaluation of all petroleum containing above ground and underground storage tanks, analysis of potential impacts from a catastrophic discharge from a tank, and preparation of recommendations to minimize the likelihood of a spill and its impacts.
Client: Moseley, Harris, McClintock Group
Fees: $12,000
Completion Date: 7/1999

 

UST AST

 

 
     